Kindred Healthcare St. Rose Dominican Hospital
– St. Rose de Lima Campus Hospital Remodels
Throughout the construction of several phased renovations throughout the existing Same Day Surgery (SDS) unit and medical/surgical areas of the hospital, PENTA maintained constant communication with the design team, Owners, and department heads.
The first phase included demolition of three existing patient/exam rooms in the SDS unit and construction of a new Sterile Processing Department (SPD). This involved working in and around the SDS, GI procedure rooms, staff locker rooms, and MD lounge. Once the new SPD was built, the project team relocated equipment to the new SPD, receiving final inspections from the State Fire Marshal and HCQC.
Phase II consisted of demolition on the existing Level 3 medical/surgical floor to allow for construction of the new pharmacy and LTAC unit. As pharmacy licensing can take several weeks and the fact this was a very fast-paced project, the team could not wait until the entire LTAC area was built in order to begin the process. Therefore, the pharmacy was certified approximately two weeks before the LTAC.
The next phase was to construct the new LTAC unit. The structure was built in the 1950s, so challenges our team encountered included constricted space above ceilings and asbestos and lead abatement.
Our daily meetings focused on potential departmental impacts and nighttime construction activities, as well as any Owner/Architect changes. Due to the fast-track project schedule, PENTA worked diligently with the design team, Owner, City and State Building and Life Safety Departments, and the HCQC and State Fire Marshal’s Department to meet the project deadline while remaining within budget.